The 750 kV transmission line project of Yili -- Bozhou -- Wusu -- Fenghuang Ⅱ is the key project of Xinjiang's "14th Five-Year Plan" economic and social development plan, and also conforms to the strategic goal of Xinjiang's superior resources conversion. The project starts from 750 kV Yili substation and ends at Phoenix 750 kV substation. The line passes through Nilk County, Jinghe County and other 8 counties, with a length of about 421 kilometers. The construction started on June 20, 2021, and it is planned to be completed and put into operation on June 20, 2023.
After the line project is put into operation, the power transmission capacity of the transmission channel will be effectively improved, and the cross-prefecture optimal allocation of energy resources will be realized, so as to meet the load demand of Xinjiang power grid, improve the stable operation level of the power grid, and provide reliable power support for economic and social development.
However, in the construction of power transmission and transformation projects through the natural environment, how to maximize the protection of nature?
In order to protect the ecological environment of Tianshan Mountain, State Grid Xinjiang Electric Power Co., Ltd. actively practices the concept of green development, runs the ecological consciousness through the whole cycle of project construction, and adopts breakthrough technological means to effectively protect the ecology of Tianshan Mountain in Xinjiang during construction.
The project has 23 kilometers of lines and 57 pylons located in the Montmarra Forest Park. The vegetation of Mommara Forest park is dominated by Xueling spruce, which is called a miniature reservoir, and plays an important role in water conservation and ecological improvement. In order to protect the ecological environment, Yili - Bozhou - Wusu - Phoenix Ⅱ back 750 kV power transmission and transformation project from the beginning of the design, it was determined to protect the forest as an important design factor, through many field investigations, the design of the line was adjusted, the project eventually circumvented about 2 kilometers, effectively avoiding more than 2000 snow mountain spruce.
In this section, the mountain is steep and winding, and the project construction is faced with many corner towers and frequent problems of high pressure gear and jump gear during wire deployment. In order to ensure the smooth development of wire deployment, State Grid Xinjiang Electric Power Co., LTD has selected experienced full-time staff to stick to the site. Measures such as optimizing the location of the stretch site, reducing the tension of the wire, using the wire pressing block, hanging the double string reinforcing block and monitoring by the UAV are taken to ensure the smooth completion of the guide ground wire deployment.
"Considering the large altitude span between the engineering towers, it is easy to run the line. We strictly controlled the distance of the laying out section according to the terrain and elevation difference of the laying out section. By increasing the short-distance laying out, the laying out section was reduced from 9 km to 4 km. At the same time, the UAV will be used to release the traction rope, which will not fall to the ground during the whole process, so as to prevent the spruce from being damaged and protect the ecology along the line." The project owner project manager Li Jun said.
When crossing the spruce, in order to timely grasp the green construction situation of the site, the project adopts centralized control intelligent visual stretch setting out method, which can realize the digital functions of stretch field management visualization, operation mutual control, data exchange and so on. Through remote video monitoring, the whole process can supervise the spruce growth environment.